Intel Ronler Acres

Intel_Ronler_Acres_Birdseye.jpg

The Industrial facility expansion at the Ronler Acres Campus required an existing stream to be destroyed. GreenWorks collaborated with a team of planners, engineers, biologists, and hydrologists to design a new path for the stream, creating and restoring a natural Ash Forest wetland to meet state and federal permit requirements.

The project also required the design of stormwater treatment facilities between the developed portion of the site and the newly created Ash Forest wetland area. GreenWorks developed a site concept plan that incorporated the wetland area and stormwater facilities into the overall campus layout and provided conceptual design information for a pedestrian bridge crossing of the new wetland area. GreenWorks also provided construction documents and construction observation for the improvements.