Pioneer Neighborhood Park Construction Update
/The rains came early this year and are proving to be a challenge for construction, but we are slowly making progress. Below are some photos that document the development. The “welcome plaza” is formed and ready for concrete, the play area is waiting for drier weather so the contractor can auger the footing holes for the play equipment, and the nature play area is beginning to take shape with the installation of exploration logs and boulders. The delivery of this friendly red-legged frog will enhance the character and add to the creative fun in the nature play area. The crushed rock forest loop path is complete.
Construction is scheduled to wrap up mid-November. Stay tuned for future updates as we work toward improving this neighborhood park.
General Contractor: Earthworks Excavation & Construction, Inc.
Client: Tualatin Hills Park & Recreation District